BetaActiveSolarPJMLBNL
16 MW generation in Westmoreland, VA · In queue since September 2021 · Proposed COD December 2022
16 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 3m
Schedule
40 months past proposed COD
In Study38%
Queue EntrySep 13, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-15
Project Details
State
VA
County
Westmoreland
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Oak Grove 34.5 kV
Data Source
LBNL
No news available for this project.