— Project Summary

Queue ID
PJM-AH1-591
Capacity
50 MW
Technology
Solar
Status
active
Location
Grant, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

50 MW generation in Grant, WV · In queue since September 2021 · Proposed COD December 2024

50 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 3m

Schedule

16 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-16

Project Details

State

WV

County

Grant

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Cherry Ridge 66kV

Data Source

LBNL

No news available for this project.