— Project Summary

Queue ID
PJM-AH1-540
Capacity
165 MW
Technology
Solar
Status
active
Location
Ogle, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

165 MW generation in Ogle, IL · In queue since September 2021 · Proposed COD March 2025

165 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

13 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-01

Project Details

State

IL

County

Ogle

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Byron to Wayne 345 kV

Data Source

LBNL

No news available for this project.