BetaActiveSolarBatteryPJMLBNL
80 MW hybrid in Carroll, OH · In queue since September 2021 · Proposed COD October 2025
80 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 1m
Schedule
5 months past proposed COD
In Study38%
Queue EntrySep 11, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-31
Project Details
State
OH
County
Carroll
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
South Canton - Sammis 345 kV
Data Source
LBNL
No news available for this project.