— Project Summary

Queue ID
PJM-AH1-526
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Carroll, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

80 MW hybrid in Carroll, OH · In queue since September 2021 · Proposed COD October 2025

80 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 1m

Schedule

5 months past proposed COD

In Study38%
Queue EntrySep 11, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-31

Project Details

State

OH

County

Carroll

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

South Canton - Sammis 345 kV

Data Source

LBNL

No news available for this project.