— Project Summary

Queue ID
PJM-AH1-452
Capacity
19.9 MW
Technology
Solar
Status
active
Location
Armstrong, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

19.9 MW generation in Armstrong, PA · In queue since September 2021 · Proposed COD June 2023

19.9 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

1y 9m

Schedule

34 months past proposed COD

In Study38%
Queue EntrySep 11, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-06-01

Project Details

State

PA

County

Armstrong

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Clementine-Clementine Jct. 25 kV

Data Source

LBNL

No news available for this project.