BetaActiveBatteryPJMLBNL
34 MW storage in Cumberland, VA · In queue since September 2021 · Proposed COD September 2026
34 MW
Capacity
1
Components
Battery
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5 years
In Study38%
Queue EntrySep 10, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
VA
County
Cumberland
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Buckingham- Farmville 230kV
Data Source
LBNL
No news available for this project.