— Project Summary

Queue ID
PJM-AH1-428
Capacity
40 MW
Technology
Battery
Status
active
Location
Boone, KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL

40 MW storage in Boone, KY · In queue since September 2021 · Proposed COD September 2026

40 MW

Capacity

1

Components

Battery

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5 years

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

Project Details

State

KY

County

Boone

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Tommy Gooch - Garrard County 69 kV

Data Source

LBNL

No news available for this project.