BetaActiveBatteryPJMLBNL
32.3 MW storage in Nicholas, WV · In queue since September 2021 · Proposed COD December 2023
32.3 MW
Capacity
1
Components
Battery
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 3m
Schedule
27 months past proposed COD
In Study38%
Queue EntrySep 11, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
WV
County
Nicholas
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Jones Branch 138 kV
Data Source
LBNL
No news available for this project.