BetaActiveWindPJMLBNL
150 MW generation in Hampshire, WV · In queue since September 2021 · Proposed COD January 2025
150 MW
Capacity
1
Components
Wind
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 4m
Schedule
15 months past proposed COD
In Study38%
Queue EntrySep 10, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-09
Project Details
State
WV
County
Hampshire
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Meadowbrook-Mount Storm 500kV
Data Source
LBNL
No news available for this project.