BetaActiveBatteryPJMLBNL
50 MW storage in Woodford, IL · In queue since September 2021 · Proposed COD September 2024
50 MW
Capacity
1
Components
Battery
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3 years
Schedule
19 months past proposed COD
In Study38%
Queue EntrySep 10, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-10
Project Details
State
IL
County
Woodford
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Minonk 345 kV
Data Source
LBNL
No news available for this project.