BetaActiveSolarPJMLBNL
80 MW generation in Wyandot, OH · In queue since September 2021 · Proposed COD November 2025
80 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 2m
Schedule
4 months past proposed COD
In Study38%
Queue EntrySep 10, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-21
Project Details
State
OH
County
Wyandot
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
West Crawford 69 kV
Data Source
LBNL
No news available for this project.