New Sub S2354 138kV — Project Summary

Queue ID
PJM-AH1-338 - moved to TC2
Capacity
180 MW
Technology
Solar
Status
active
Location
Lee, IL
Region
PJM
Developer
IA Status

New Sub S2354 138kV

BetaActiveSolarPJMLive · PJM

180 MW generation in Lee, IL · In queue since February 2025

180 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 1m

Pre-Study0%
Queue EntryFeb 13, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

IL

County

Lee

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Data Source

Live · PJM

No news available for this project.