— Project Summary

Queue ID
PJM-AH1-338
Capacity
180 MW
Technology
Solar
Status
active
Location
Lee, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

180 MW generation in Lee, IL · In queue since September 2021 · Proposed COD November 2025

180 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 2m

Schedule

4 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-21

Project Details

State

IL

County

Lee

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

New Sub S2354 138kV

Data Source

LBNL

No news available for this project.