Hardin Switch 345 kV — Project Summary

Queue ID
PJM-AH1-327 - moved to TC2
Capacity
250 MW
Technology
Solar
Status
active
Location
Hardin, OH
Region
PJM
Developer
IA Status

Hardin Switch 345 kV

BetaActiveSolarPJMLive · PJM

250 MW generation in Hardin, OH · In queue since February 2025

250 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection Timeline

Total Duration

1y 1m

Pre-Study0%
Queue EntryFeb 18, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OH

County

Hardin

Region

PJM

Developer

Utility

AEP

Entity

PJM

Data Source

Live · PJM

No news available for this project.