— Project Summary

Queue ID
PJM-AH1-304
Capacity
9.8 MW
Technology
Solar
Status
active
Location
Delaware, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

9.8 MW generation in Delaware, IN · In queue since September 2021 · Proposed COD December 2023

9.8 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 3m

Schedule

27 months past proposed COD

In Study38%
Queue EntrySep 11, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

IN

County

Delaware

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Delaware-Van Buren 138 kV

Data Source

LBNL

No news available for this project.