— Project Summary

Queue ID
PJM-AH1-298
Capacity
75 MW
Technology
Battery
Status
active
Location
Whitley, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL

75 MW storage in Whitley, IN · In queue since September 2021 · Proposed COD December 2025

75 MW

Capacity

1

Components

Battery

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 3m

Schedule

3 months past proposed COD

In Study38%
Queue EntrySep 14, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

IN

County

Whitley

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Twin Branch - Meridian 345 kV

Data Source

LBNL

No news available for this project.