BetaActiveSolarPJMLBNL
20 MW generation in Nelson, KY · In queue since September 2021 · Proposed COD June 2024
20 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 9m
Schedule
22 months past proposed COD
In Study38%
Queue EntrySep 9, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-07
Project Details
State
KY
County
Nelson
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Bluegrass Parkway Tap - Woodlawn 69 kV
Data Source
LBNL
No news available for this project.