BetaActiveSolarPJMLBNL
300 MW generation in Van Buren, MI · In queue since September 2021 · Proposed COD May 2025
300 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 8m
Schedule
11 months past proposed COD
In Study38%
Queue EntrySep 10, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-01
Project Details
State
MI
County
Van Buren
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Argenta - Twin Branch 345 kV
Data Source
LBNL
No news available for this project.