— Project Summary

Queue ID
PJM-AH1-272
Capacity
300 MW
Technology
Solar
Status
active
Location
Van Buren, MI
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

300 MW generation in Van Buren, MI · In queue since September 2021 · Proposed COD May 2025

300 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 8m

Schedule

11 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-01

Project Details

State

MI

County

Van Buren

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Argenta - Twin Branch 345 kV

Data Source

LBNL

No news available for this project.