Cashie 230 kV
BetaActiveSolarPJMLive · PJM
110 MW generation in Bertie, NC · In queue since February 2025
110 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 1m
Pre-Study0%
Queue EntryFeb 7, 2025
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
Bertie
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Data Source
Live · PJM
No news available for this project.