300 MW storage in Camden, NJ · In queue since September 2021 · Proposed COD June 2025
300 MW
Capacity
1
Components
Battery
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 9m
Schedule
9 months past proposed COD
In Study38%
Queue EntrySep 10, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-30
Project Details
State
NJ
County
Camden
Region
PJM
Developer
—
Utility
PSEG
Entity
PJM
Point of Interconnection
New Freedom 230 kV
Data Source
LBNL