Port Belford Solar Farm — Project Summary

Queue ID
PJM-AH1-258
Capacity
19.25 MW
Technology
Solar
Status
active
Location
Monmouth, NJ
Region
PJM
Developer
IA Status
In Progress (unknown study)

Port Belford Solar Farm

BetaActiveSolarPJMLBNL

19.25 MW generation in Monmouth, NJ · In queue since September 2021 · Proposed COD December 2022

19.25 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 3m

Schedule

40 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-23

Project Details

State

NJ

County

Monmouth

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Belford - Keansburg 34.5 kV

Data Source

LBNL

No news available for this project.