— Project Summary

Queue ID
PJM-AH1-254
Capacity
207.6 MW
Technology
Wind
Status
active
Location
Barbour, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveWindPJMLBNL

207.6 MW generation in Barbour, WV · In queue since September 2021 · Proposed COD July 2025

207.6 MW

Capacity

1

Components

Wind

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 10m

Schedule

8 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-31

Project Details

State

WV

County

Barbour

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Greenland Gap 500 kV II

Data Source

LBNL

No news available for this project.