Remington CT 230 kV
BetaActiveStoragePJMLive · PJM
100 MW storage in Fauquier, VA · In queue since February 2025 · Proposed COD September 2029
100 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 7m
Pre-Study0%
Queue EntryFeb 25, 2025
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-01
Project Details
State
VA
County
Fauquier
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Data Source
Live · PJM
No news available for this project.