— Project Summary

Queue ID
PJM-AH1-215
Capacity
31.5 MW
Technology
Solar+Battery
Status
active
Location
Charlotte, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

31.5 MW hybrid in Charlotte, VA · In queue since September 2021 · Proposed COD February 2025

31.5 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 5m

Schedule

14 months past proposed COD

In Study38%
Queue EntrySep 9, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-02-01

Project Details

State

VA

County

Charlotte

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Central VA-Twitty 115 kV

Data Source

LBNL

No news available for this project.