— Project Summary

Queue ID
PJM-AH1-201
Capacity
40 MW
Technology
Solar
Status
active
Location
Somerset, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

40 MW generation in Somerset, PA · In queue since September 2021 · Proposed COD August 2023

40 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

1y 11m

Schedule

31 months past proposed COD

In Study38%
Queue EntrySep 3, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-08-31

Project Details

State

PA

County

Somerset

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

New Baltimore 115 kV (Mountain Ridge Solar)

Data Source

LBNL

No news available for this project.