— Project Summary

Queue ID
PJM-AH1-197
Capacity
7.1 MW
Technology
Other
Status
active
Location
Fairfax, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveOtherPJMLBNL

7.1 MW generation in Fairfax, VA · In queue since September 2021 · Proposed COD August 2021

7.1 MW

Capacity

1

Components

Other

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

4y 6m

Schedule

56 months past proposed COD

In Study38%
Queue EntrySep 1, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-08-20

Project Details

State

VA

County

Fairfax

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Occoquan 230kV

Data Source

LBNL

No news available for this project.