— Project Summary

Queue ID
PJM-AH1-196
Capacity
150 MW
Technology
Solar
Status
active
Location
Mchenry, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

150 MW generation in Mchenry, IL · In queue since September 2021 · Proposed COD December 2026

150 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 3m

In Study38%
Queue EntrySep 2, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-15

Project Details

State

IL

County

Mchenry

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Garden Prairie 345 kV

Data Source

LBNL

No news available for this project.