— Project Summary

Queue ID
PJM-AH1-188
Capacity
185 MW
Technology
Solar+Battery
Status
active
Location
Mingo, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

185 MW hybrid in Mingo, WV · In queue since August 2021 · Proposed COD June 2025

185 MW

Capacity

1

Components

Solar

4y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 10m

Schedule

10 months past proposed COD

In Study38%
Queue EntryAug 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

WV

County

Mingo

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Pigeon Creek 138 kV

Data Source

LBNL

No news available for this project.