80 MW storage in Will, IL · In queue since August 2021 · Proposed COD June 2025
80 MW
Capacity
1
Components
Battery
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 10m
Schedule
10 months past proposed COD
In Study38%
Queue EntryAug 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
IL
County
Will
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Will County 138 kV
Data Source
LBNL