BetaActiveSolarPJMLBNL
65 MW generation in Franklin, VA · In queue since August 2021 · Proposed COD December 2024
65 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 4m
Schedule
15 months past proposed COD
In Study38%
Queue EntryAug 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-20
Project Details
State
VA
County
Franklin
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Oak Level - Tank Hill 138 kV
Data Source
LBNL
No news available for this project.