— Project Summary

Queue ID
PJM-AH1-164
Capacity
65 MW
Technology
Solar
Status
active
Location
Franklin, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

65 MW generation in Franklin, VA · In queue since August 2021 · Proposed COD December 2024

65 MW

Capacity

1

Components

Solar

4y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 4m

Schedule

15 months past proposed COD

In Study38%
Queue EntryAug 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-20

Project Details

State

VA

County

Franklin

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Oak Level - Tank Hill 138 kV

Data Source

LBNL

No news available for this project.