— Project Summary

Queue ID
PJM-AH1-162
Capacity
16 MW
Technology
Solar
Status
active
Location
Bedford, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

16 MW generation in Bedford, PA · In queue since August 2021 · Proposed COD November 2023

16 MW

Capacity

1

Components

Solar

4y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 3m

Schedule

29 months past proposed COD

In Study38%
Queue EntryAug 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-11-01

Project Details

State

PA

County

Bedford

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Curryville-RKB-Yellow Creek 23 kV

Data Source

LBNL

No news available for this project.