BetaActiveSolarPJMLBNL
20 MW generation in Tioga, PA · In queue since August 2021 · Proposed COD November 2023
20 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 3m
Schedule
29 months past proposed COD
In Study38%
Queue EntryAug 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-01
Project Details
State
PA
County
Tioga
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Tower Hill 34.5 kV
Data Source
LBNL
No news available for this project.