BetaActiveBatteryPJMLBNL
30 MW storage in Venango, PA · In queue since September 2021 · Proposed COD August 2023
30 MW
Capacity
1
Components
Battery
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 11m
Schedule
31 months past proposed COD
In Study38%
Queue EntrySep 1, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-08-31
Project Details
State
PA
County
Venango
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Eclipse-Piney 115 kV III
Data Source
LBNL
No news available for this project.