BetaActiveBatteryPJMLBNL
100 MW storage in York, VA · In queue since August 2021 · Proposed COD January 2025
100 MW
Capacity
1
Components
Battery
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 5m
Schedule
15 months past proposed COD
In Study38%
Queue EntryAug 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
VA
County
York
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Penniman - Waller 230 kV
Data Source
LBNL
No news available for this project.