BetaActiveSolarPJMLBNL
200 MW generation in Lee, IL · In queue since August 2021 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 4m
Schedule
3 months past proposed COD
In Study38%
Queue EntryAug 27, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
IL
County
Lee
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Nelson-Electric Junction 345 kV
Data Source
LBNL
No news available for this project.