Peter's Mountain 138 kV — Project Summary

Queue ID
PJM-AH1-145 - moved to TC2
Capacity
150 MW
Technology
Battery
Status
active
Location
Giles, VA
Region
PJM
Developer
IA Status

Peter's Mountain 138 kV

BetaActiveStoragePJMLive · PJM

150 MW storage in Giles, VA · In queue since March 2025

150 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 7, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

VA

County

Giles

Region

PJM

Developer

Utility

AEP

Entity

PJM

Data Source

Live · PJM

No news available for this project.