BetaActiveGasPJMLBNL
9 MW generation in City Of Richmond, VA · In queue since August 2021 · Proposed COD June 2022
9 MW
Capacity
1
Components
Gas
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
10 months
Schedule
46 months past proposed COD
In Study38%
Queue EntryAug 4, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-01
Project Details
State
VA
County
City Of Richmond
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Spruance NUG 230 kV
Data Source
LBNL