Wolf Glade-West Carroll 138 kV
BetaActiveSolar; StoragePJMLive · PJM
40 MW generation in Carroll, VA · In queue since July 2025
40 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
8 months
Pre-Study0%
Queue EntryJul 1, 2025
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
VA
County
Carroll
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Data Source
Live · PJM
No news available for this project.