BetaActiveSolarBatteryPJMLBNL
40 MW hybrid in Carroll, VA · In queue since July 2021 · Proposed COD June 2025
40 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 11m
Schedule
10 months past proposed COD
In Study38%
Queue EntryJul 30, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
VA
County
Carroll
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Jubal Early - Pipers Gap 138 kV
Data Source
LBNL
No news available for this project.