— Project Summary

Queue ID
PJM-AH1-094
Capacity
49.9 MW
Technology
Solar+Battery
Status
active
Location
Huron, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

49.9 MW hybrid in Huron, OH · In queue since July 2021 · Proposed COD June 2025

49.9 MW

Capacity

1

Components

Solar

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 11m

Schedule

10 months past proposed COD

In Study38%
Queue EntryJul 30, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

OH

County

Huron

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Wells - Shinrock 69 kV I

Data Source

LBNL