Summersweet Energy Center, LLC — Project Summary

Queue ID
PJM-AH1-088
Capacity
20 MW
Technology
Battery
Status
active
Location
Fauquier, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

Summersweet Energy Center, LLC

BetaActiveBatteryPJMLBNL

20 MW storage in Fauquier, VA · In queue since July 2021 · Proposed COD July 2023

20 MW

Capacity

1

Components

Battery

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2 years

Schedule

32 months past proposed COD

In Study38%
Queue EntryJul 30, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-07-31

Project Details

State

VA

County

Fauquier

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Morrisville 230kV

Data Source

LBNL

No news available for this project.