44 MW generation in Metcalfe, KY · In queue since July 2021 · Proposed COD December 2024
44 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 5m
Schedule
15 months past proposed COD
In Study38%
Queue EntryJul 30, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-20
Project Details
State
KY
County
Metcalfe
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Knob Lick 69kV
Data Source
LBNL