— Project Summary

Queue ID
PJM-AH1-071
Capacity
20 MW
Technology
Solar
Status
active
Location
Powhatan, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

20 MW generation in Powhatan, VA · In queue since July 2021 · Proposed COD July 2023

20 MW

Capacity

1

Components

Solar

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2 years

Schedule

33 months past proposed COD

In Study38%
Queue EntryJul 29, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-07-01

Project Details

State

VA

County

Powhatan

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Midlothian 34.5 kV

Data Source

LBNL

No news available for this project.