BetaActiveSolarPJMLBNL
7.2 MW generation in Wicomico, MD · In queue since July 2021 · Proposed COD January 2023
7.2 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 6m
Schedule
38 months past proposed COD
In Study38%
Queue EntryJul 15, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-01-31
Project Details
State
MD
County
Wicomico
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Edgewood 12.47 kV
Data Source
LBNL
No news available for this project.