BetaActiveSolarPJMLBNL
100 MW generation in Campbell, VA · In queue since July 2021 · Proposed COD November 2026
100 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 4m
In Study38%
Queue EntryJul 14, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-11-15
Project Details
State
VA
County
Campbell
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Red House D.P. 115kV
Data Source
LBNL