— Project Summary

Queue ID
PJM-AH1-056
Capacity
100 MW
Technology
Solar
Status
active
Location
Campbell, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

100 MW generation in Campbell, VA · In queue since July 2021 · Proposed COD November 2026

100 MW

Capacity

1

Components

Solar

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 4m

In Study38%
Queue EntryJul 14, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-15

Project Details

State

VA

County

Campbell

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Red House D.P. 115kV

Data Source

LBNL