BetaActiveSolarPJMLBNL
220 MW generation in Jackson, OH · In queue since July 2021 · Proposed COD November 2026
220 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 4m
In Study38%
Queue EntryJul 14, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-11-15
Project Details
State
OH
County
Jackson
Region
PJM
Developer
—
Utility
OVEC
Entity
PJM
Point of Interconnection
Kyger Creek - Don Marquis 345 kV
Data Source
LBNL
No news available for this project.