8.25 MW generation in Ocean, NJ · In queue since July 2021 · Proposed COD July 2022
8.25 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1 year
Schedule
45 months past proposed COD
In Study38%
Queue EntryJul 9, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-07-08
Project Details
State
NJ
County
Ocean
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Upton-Whitings 34.5 kV
Data Source
LBNL