BetaActiveSolarPJMLBNL
50 MW generation in Venango, PA · In queue since July 2021 · Proposed COD July 2023
50 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2 years
Schedule
33 months past proposed COD
In Study38%
Queue EntryJul 7, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-07-01
Project Details
State
PA
County
Venango
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Eclipse-Piney 115 kV
Data Source
LBNL
No news available for this project.