— Project Summary

Queue ID
PJM-AH1-047
Capacity
61.6 MW
Technology
Solar
Status
active
Location
Boone, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

61.6 MW generation in Boone, IL · In queue since July 2021 · Proposed COD September 2022

61.6 MW

Capacity

1

Components

Solar

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 2m

Schedule

43 months past proposed COD

In Study38%
Queue EntryJul 6, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-09-13

Project Details

State

IL

County

Boone

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Marengo - Belvidere 138 kV

Data Source

LBNL

No news available for this project.