BetaActiveSolarPJMLBNL
61.6 MW generation in Boone, IL · In queue since July 2021 · Proposed COD September 2022
61.6 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 2m
Schedule
43 months past proposed COD
In Study38%
Queue EntryJul 6, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-09-13
Project Details
State
IL
County
Boone
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Marengo - Belvidere 138 kV
Data Source
LBNL
No news available for this project.