BetaActiveSolarPJMLBNL
23 MW generation in Lake, IL · In queue since July 2021 · Proposed COD June 2023
23 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 11m
Schedule
34 months past proposed COD
In Study38%
Queue EntryJul 1, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
IL
County
Lake
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Zion Energy Center 345 kV
Data Source
LBNL
No news available for this project.